Works on finishes started in Worcester

Pellikaan is building a new David Lloyd Club next to the Worcester Warrior’s Stadium. The centre is being constructed using a steel structure, with a metal deck first floor, composite panel walls and aluminium frame elevations. The external facade of the building comprises of facing brickwork whilst the roof includes standard seam roofing. At the moment, the roof has been finished and the last aluminium frames are being put up, so the building envelope is almost completed. Inside the building, finishes works have started: the partitions are nearly all installed, the installations are well on schedule, and works on ceilings and tiling have commenced. Externally, three of the five tennis court are ready, the last two are currently being laid.